Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
A project manager is trying to convince management to use more formal project management procedures and has decided to start improving the company’s project management by obtaining a project charter for each of his projects. Which of the following best describes how a project charter would help the project manager?
|
It describes the details of what needs to be done.
|
|
It lists the names of all team members.
|
|
It gives the project manager authority.
|
|
It describes the history of similar or related projects.
|
Explanation:
Detailed explanation-1: -A project charter is a formal short document that states a project exists and provides project managers with written authority to begin work. A project charter document describes a project to create a shared understanding of its goals, objectives and resource requirements before the project is scoped out in detail.
Detailed explanation-2: -Which of the following is the BEST method to achieve a realistic project management plan? If we were to rephrase the question, it is asking, “Who creates the project management plan?” The best answer is that project management plans are created by the project manager but require input from the team. 17.