An activity has an early start date of the 10th and a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?
A
Total float for the activity is nine days.
B
The early finish date of the activity is the end of the day on the 14th.
C
The late finish date is the 25th.
D
The activity can be completed in two days if the resources devoted to it are doubled.
Explanation: 

Detailed explanation-1: -The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity? Total float for the activity is nine days.