Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
A work authorization system can be used to:
A
Manage who does each activity.
B
Manage when and in what sequence work is done.
C
Manage when each activity is done.
D
Manage who does each activity and when it is done.
Explanation: 

Detailed explanation-1: -A work authorization system is used to coordinate when and in what order the work is performed so that work and people may adequately interface with other work and other people.

Detailed explanation-2: -The work authorization system is used by the project manager and his or her designees in order to approve all project work throughout the course of the current project management venture.

Detailed explanation-3: -The monitoring & controlling project management process group governs the tasks and steps in three key areas: tracking, reviewing and optimizing project progress and performance; identifying areas in which changes to the project plan are beneficial or necessary; and carrying out approved changes.

Detailed explanation-4: -Explanation: The project charter does several important things: it lays out the project requirements, describes an initial summary milestone schedule, documents the business case and identifies initial risks, assumptions and constraints.

Detailed explanation-5: -The best thing for the project manager to do is begin the Close Project or Phase process. All of the following are parts of an effective change management plan EXCEPT: A.