SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

PROJECT SCHEDULING AND TRACKING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is included in a project charter?
A
A risk management strategy
B
Work package estimates
C
Detailed resource estimates
D
The business case for the project
Explanation: 

Detailed explanation-1: -Which of the following must be included in the project charter? Answer C is correct. The product description is one of the three requirements of the project charter, as described by the PMBOK. The other alternatives may appear in some organization’s charters, but these vary and are not mandated by PMI.

Detailed explanation-2: -An important point to observe is that the creation of a project charter encompasses all the project areas including, scope, risk, time, cost, quality, human resources, communications, and procurement). Thus, making the Develop Project Charter an integration process.

There is 1 question to complete.