Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Although the customer agreed to the original project schedule, they are now asking for an earlier project finish. They are being pressured by their own customers. ·the project manager’s sponsor thinks finishing early is not only a viable option but also a good idea for your organization because it will enable you to start another project sooner. In attempting to complete the project faster, the project manager looks at the cost associated with crashing each activity. 1he best approach to crashing would also include looking at the
A
Rick imp.1ct of crashing each activity
B
Customer opinion of which activities to crash
C
Sponsor’s opinion of which activities to crash and in what order
D
Project life cycle phase in which the activity 1s due to occur
Explanation: 

Detailed explanation-1: -Questions such as “What is their personality like?” “What are their triggers (e.g., cost, schedule, quality)?” “What do they define as success?” “What outcome do they hope to achieve with this project?” “To what level of granularity do they want to or are willing to be involved?” all run through my head.

Detailed explanation-2: -Logical relationship Finish-to-finish–the “from” activity must finish before the “to” activity can finish.

Detailed explanation-3: -Step 1: Create a Work Breakdown Structure (WBS) A Work Breakdown Structure (WBS) is used for estimating the project scope by breaking it down into easily manageable components, or bites. WBS is the hierarchical list of project’s phases, tasks, and milestones.