SOFTWARE PROJECT MANAGEMENT
PROJECT SCHEDULING AND TRACKING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Knowledge management is a key responsibility of the project manager. This responsibility includes managing two kinds of knowledge on a project:tacit and explicit. Which of the following definitions are correct?
|
Tacit knowledge is fact-based and can be easily communicated through words and symbols.
|
|
Tacit knowledge may need explanation or context to provide value to recipients of this information.
|
|
Tacit knowledge includes emotions, experience, and abilities.
|
|
Lessons learned are an example of tacit knowledge.
|
Explanation:
Detailed explanation-1: -The definition of knowledge management also includes three types of knowledge-tacit, implicit, and explicit knowledge. These types of knowledge are largely distinguished by the codification of the information.
Detailed explanation-2: -Learning how to speak another language. Innovation. Aesthetic Sense. Leadership. Sales. 24-Dec-2021
There is 1 question to complete.