An example of a mandatory dependency is:
A
A dependency established based on knowledge of best practices within a particular application area.
B
A dependency established based on some unusual aspect of the project where a specific sequence is desired.
C
On a construction project, to erect the superstructure only after the foundation has been built.
D
On a software development project, to start design only after completion and approval of all project requirements.
Explanation: 

Detailed explanation-1: -A mandatory dependency is one that “must be” carried out at a particular time. It is usually requirement of some kind based on contracts, laws, company procedures, physical limitations, etc.

Detailed explanation-2: -A dependency requiring that design be completed before manufacturing can start is an example of a(n): Scope Dependency.