Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
A design engineer is helping to ensure that the dependencies within her area of expertise .ire properly defined on the project. The design of several deliverables must be complete before manufacturing can begin. This is an example of what type of dependency?
A
Discretionary dependency
B
External dependency
C
Mandatory dependency
D
Scope dependency
Explanation: 

Detailed explanation-1: -The project control process starts with establishing a baseline plan that shows how the project scope will be accomplished on schedule and over budget. A change in the estimated duration of any activity on that path will cause a corresponding change in the slack for that path.

Detailed explanation-2: -A Gantt chart is a visual representation of all the tasks related to your project scheduled overtime. They are used to plan projects of all sizes and shapes. Why? Because they are an incredible tool to show the work that is scheduled to be done on a project on a specific day.

Detailed explanation-3: -(41) Which of the following methods is least likely to be used for explaining project planning guidelines to the team? Hint − A report gives information about what happened and doesn’t talk about planning or give guidelines or directives.