Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Approved corrective actions are an input to which of the following processes?
A
Validate Scope
B
Direct and Manage Project Work
C
Develop Project Charter
D
Develop Schedule
Explanation: 

Detailed explanation-1: -Get all team members together into a cohesive whole. Approved corrective actions are an input to which of the following processes? Explanation: Direct and Manage Project Work is the only correct response.

Detailed explanation-2: -Deliverables: An approved deliverable is one of the most important outputs of this process. It is any unique and verifiable product, result or capability to perform a service that must be produced to complete a phase, process or project.

Detailed explanation-3: -Performing the work to achieve project objectives. Creating project deliverables. Managing technical and organisational interfaces. Generating work performance data Reporting performance. Managing the risks, team, stakeholder expectations, sellers, contractors. More items

There is 1 question to complete.