Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Assume you are working on a on a project using lean manufacturing. Now you are preparing your schedule. You feel your tasks may be relatively similar in size and scope. You should consider-
|
Fixed number of work periods
|
|
Percent of the estimated activity duration
|
|
Buffers
|
|
Kanban system
|
Explanation:
Detailed explanation-1: -Kanban Cards – This is the visual representation of tasks. Each card contains information about the task and its status, such as deadline, assignee, description, etc. Kanban Columns – Each column on the board represents a different stage of your workflow.
Detailed explanation-2: -There are 4 principles of Kanban, which assist in creating the Kanban Board and help to ensure that the team is always working on the most valuable tasks. They are: Visualize the Work, Limit the Work in Progress (WIP), Focus on Flow, and Continuous Improvement.