SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

PROJECT SCHEDULING AND TRACKING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You arc the project manager for a new product development project that has four levels in the work breakdown structure. The network diagram and duration estimates have been created, and a schedule has been developed and compressed. Which schedule management activity should you do next?
A
Control the schedule
B
Determine dependencies
C
Analogously estimate the schedule.
D
Gain approval.
Explanation: 

Detailed explanation-1: -Critical path method (CPM) A network analysis technique used to predict project duration by analyzing which sequence of activities (which path) has the least amount of scheduling flexibility (the least amount of total float).

Detailed explanation-2: -A network diagram allows a project manager to track each element of a project and quickly share its status with others. Its other benefits include: Visual representation of progress for stakeholders. Establishing project workflows.

There is 1 question to complete.