Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Consider the following information about the duration of an activity:Calculated expected (IE) = 5 weeksOptimistic (tO) = 4 weeksPessimistic (tP) = 8 weeksUsing the beta distribution and the three-point estimating approach, the Most likely (tM) activity duration is:
A
4.0 weeks.
B
4.5 weeks.
C
5.0 weeks.
D
6.0 weeks.