SOFTWARE PROJECT MANAGEMENT
PROJECT SCHEDULING AND TRACKING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Consider the following information about the duration of an activity:Calculated expected (IE) = 5 weeksOptimistic (tO) = 4 weeksPessimistic (tP) = 8 weeksUsing the beta distribution and the three-point estimating approach, the Most likely (tM) activity duration is:
|
4.0 weeks.
|
|
4.5 weeks.
|
|
5.0 weeks.
|
|
6.0 weeks.
|
Explanation:
There is 1 question to complete.