SOFTWARE PROJECT MANAGEMENT
PROJECT SCHEDULING AND TRACKING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
Validate Scope
|
|
Plan Risk Responses
|
|
Create a staffing management plan
|
|
Complete lessons learned
|
Detailed explanation-1: -What is the first step in capturing lessons learned at the end of a project ? The project manager must send an email asking the participants to identify major project issues. What does a typical closeout report include? summary status of the project, lessons learned, review of the projects original justification.
Detailed explanation-2: -Project closure is the last phase of a project. It’s when the project manager verifies that the client, stakeholder or customer has accepted the project deliverables. If the project or product is ongoing after the project, then maintenance must be set up.
Detailed explanation-3: -Suggested categories include project management, technology, communication, business processes, requirements, design and build, testing and implementation. These categories can be subdivided into more detailed categories. For example, project management can be divided into initiation, planning, control and closing.