Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Consider the following three estimates for the duration of an activity:Optimistic (tO) = 6 weeksMost likely (tM) = 9 weeksPessimistic (IP)= 15 weeksUsing the triangular distribution, the calculated Expected activity duration (tE) is:
A
10.0 weeks.
B
10.5 weeks.
C
11.5 weeks.
D
12.0 weeks.
Explanation: 

Detailed explanation-1: -QUESTION 22 Consider the following three estimates for the duration of an activity: Optimistic (tO) 6 weeks Most likely (tM)-9 weeks Pessimistic (tP) 15 weeks Using the triangular distribution, the calculated Expected activity duration (E) is: 12.0 weeks.