You have been involved in creating the project charter, but could not get it approved. Your manager and his boss have asked that the project begin immediately. Which of the following is the best thing to do?
A
Set up an integrated change control process.
B
Show your manager the impact of proceeding without approval.
C
Focus on completing projects that have signed project charters.
D
Start work on only the critical path activities.
Explanation: 

Detailed explanation-1: -You have created the project charter but could not get it approved by senior management. Your manager and his boss have asked you to begin the project anyway. Which of the following actions is the best thing to do? Focus on other projects that have a signed charter.

Detailed explanation-2: -Who should approve the charter? Typically the Project Sponsor approves the charter by signing it (or indicating approval digitally). There may be multiple sponsors, particularly if this is a major project that requires heavy involvement from more than one department.

Detailed explanation-3: -A project charter should only include three elements: your project objectives, scope, and responsibilities.