 “Crashing” in schedule management is: 
|  |  A schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources. 
 | 
|  |  A schedule compression technique in which phases or activities that are normally done in sequence are performed in parallel. 
 | 
|  |  The timely input of data to calculate the critical path. 
 | 
|  |  Equivalent to minimizing float in the project schedule network 
 | 
 Explanation: 
Detailed explanation-1: -What is project crashing? Project crashing is a schedule compression technique in which you bring in additional resources to complete two tasks simultaneously. The Project Management Body of Knowledge (PMBOK® Guide) defines the crashing technique as a way to shorten your project schedule for the least incremental cost.
Detailed explanation-2: -The PMBOK Guide, 6th edition, defines crashing as a technique used to shorten the schedule duration for the lowest incremental cost by adding resources.
Detailed explanation-3: -According to PMBOK, schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives.