Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
“Crashing” in schedule management is:
|
A schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources.
|
|
A schedule compression technique in which phases or activities that are normally done in sequence are performed in parallel.
|
|
The timely input of data to calculate the critical path.
|
|
Equivalent to minimizing float in the project schedule network
|
Explanation:
Detailed explanation-1: -What is project crashing? Project crashing is a schedule compression technique in which you bring in additional resources to complete two tasks simultaneously. The Project Management Body of Knowledge (PMBOK® Guide) defines the crashing technique as a way to shorten your project schedule for the least incremental cost.
Detailed explanation-2: -The PMBOK Guide, 6th edition, defines crashing as a technique used to shorten the schedule duration for the lowest incremental cost by adding resources.
Detailed explanation-3: -According to PMBOK, schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives.
There is 1 question to complete.