During executing, the project manager determines that a change is needed to material purchased for the project. The project manager calls a meeting of the team to plan how to make the change. This is an example of:
A
Management by objectives
B
Lack of a change management plan
C
Good team relations
D
Lack of a clear work breakdown structure
Explanation: 

Detailed explanation-1: -If the change request is approved then the project deliverables will need to be updated. This can include plans and schedules, business process documents, and the requirements documents. Once these updates have been made, the project manager can communicate the new course of action to everyone who will be impacted.

Detailed explanation-2: -Change control informs the project manager during the planning phase of the project. They will start thinking about change and how to better respond to it and learn from their experience with change control to put more safeguards upfront in their planning for future projects.