Your sponsor and stakeholders have made it dear they wish to be kept informed on the project status. there are many aspects of the project on which you will report, and you want to choose the most appropriate tool to use in each case. which of the following:ire generally illustrated better by bar charts than network diagrams:
A
Logical relationships
B
Critical paths
C
Resource trade-offs
D
Progress or status
Explanation: 

Detailed explanation-1: -The project sponsor is the person responsible for the overall success of the project, including appointing the project manager and team, defining success criteria, and ensuring the successful delivery of the project.

Detailed explanation-2: -Sequence Activities-The process of identifying and documenting relationships among the project activities. Estimate Activity Durations-The process of estimating the number of work periods needed to complete individual activities with estimated resources.

Detailed explanation-3: -The fourth project management phase, project monitoring and control, takes place concurrently with the execution phase of the project. It involves monitoring the progress and performance of the project to ensure it stays on schedule and within budget.