Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
During project planning, you estimate the time needed for each activity and then total the estimates to create the project estimate. You commit to completing the project by this date. What b wrong with this scenario?
|
The team did not create the estimate, and estimating takes too long using that method.
|
|
The team did not create the estimate, and a network diagram was not used
|
|
The estimate is too long and should be created by management.
|
|
The project estimate should be the same as the customer’s required completion date.
|
Explanation:
Detailed explanation-1: -initiation. planning. execution. monitoring and control. closure.
Detailed explanation-2: -Review project scope. Create a list of tasks. Collect data for each task. Include external hours. Consider revision hours. Consider adding contingency hours. Add all components together. Review and revise the estimate. 10-Mar-2023
Detailed explanation-3: -Think of your plan as a roadmap for stakeholders. Break the project into a list of deliverables. Talk to your team. Identify risks. Create a budget. Add milestones. Set progress reporting guidelines.
There is 1 question to complete.