SOFTWARE PROJECT MANAGEMENT
PROJECT SCHEDULING AND TRACKING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Consider the following three estimates for the duration of an activity:Optimistic (tO) = 4 weeksMost likely (tM) = 5 weeksPessimistic (tP) = 9 weeksUsing the beta distribution and the three-point estimating approach, the calculated Expected activity duration (tE) is:
|
4.0 weeks.
|
|
4.5 weeks.
|
|
5.5 weeks.
|
|
6.5 weeks.
|
Explanation: