Consider the following three estimates for the duration of an activity:Optimistic (tO) = 4 weeksMost likely (tM) = 5 weeksPessimistic (tP) = 9 weeksUsing the beta distribution and the three-point estimating approach, the calculated Expected activity duration (tE) is:
A
4.0 weeks.
B
4.5 weeks.
C
5.5 weeks.
D
6.5 weeks.
Explanation: 