In which sort of project is the use of a Gantt chart most appropriate?
A
Projects where the time period involved are very short
B
Projects with few activities and resource involved
C
Projects with many activities involved
D
Projects in which the use of resources must be carefully monitored.
Explanation: 

Detailed explanation-1: -Gantt charts are useful for planning and scheduling projects. They help you assess how long a project should take, determine the resources needed, and plan the order in which you’ll complete tasks.

Detailed explanation-2: -A Gantt chart is a project management tool that shows project tasks on a timeline. The Gantt diagram was created by Henry Gantt in the early 20th century to improve project planning, scheduling and tracking by illustrating completed work compared to planned work.

Detailed explanation-3: -It’s a timetable that outlines start and end dates and milestones that must be met for the project to be completed on time. The project schedule is often used in conjunction with a work breakdown structure (WBS) to distribute work among team members.