In rolling wave planning:
A
Focus is maintained on long-term objectives, allowing near-term objectives to be rolled out as part of the ongoing wave of activities.
B
The work to be accomplished in the near term is planned in detail, whereas the work in the future is planned at a higher level.
C
The work far in the future is planned in detail for work packages that are at a low level of the WBS.
D
A wave of detailed activities is planned during strategic planning to ensure that WBS deliverables and project milestones are achieved.
Explanation: 

Detailed explanation-1: -According to the Guide to the Project Management Body of Knowledge (PMBOK® Guide), Rolling Wave Planning is “an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while work further in the future is planned at a higher level”.

Detailed explanation-2: -Rolling wave planning is a project management technique that breaks the work planning process into smaller waves or time periods, which makes it easier for the team to accommodate project changes. It focuses on iterative work and frequent updates.

Detailed explanation-3: -Rolling wave planning is a type of project schedule that focuses on iterative work and frequent updates to the project plan. It’s a project planning technique for projects that don’t offer all the data needed to create a plan or schedule up front. That doesn’t mean the project starts without a plan.