Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Project managers should pay attention to critical and subcritical activities when evaluating project time performance. One way to do this is to analyze 10 subcritical paths in order of ascending float. This approach is part of-
|
Variance analysis
|
|
Simulation
|
|
Earned value management
|
|
Trend analysis
|
Explanation: