Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
the float of an activity is determined by:
A
. Performing a Monte Carlo analysis
B
Determining the waiting time between activities
C
Determining lag
D
Determining the length of time the activity can be delayed without delaying the critical path
Explanation: 

Detailed explanation-1: -The critical activity has zero float.

Detailed explanation-2: -Historically, activities with zero float were defined as the critical path. This is not always the case, however. Critical path activities can have float; hence the critical path can have float.