Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
the float of an activity is determined by:
|
. Performing a Monte Carlo analysis
|
|
Determining the waiting time between activities
|
|
Determining lag
|
|
Determining the length of time the activity can be delayed without delaying the critical path
|
Explanation:
Detailed explanation-1: -The critical activity has zero float.
Detailed explanation-2: -Historically, activities with zero float were defined as the critical path. This is not always the case, however. Critical path activities can have float; hence the critical path can have float.