Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Several types of float are found in project networks. Float that is used by a particular activity and does NOT affect the float in later activities is called-
A
Extra float
B
Free float
C
Total float
D
Expected float
Explanation: 

Detailed explanation-1: -Float that is used by a particular activity and does NOT affect the float in later activities is called: Extra float Free float Total float Expected float.

Detailed explanation-2: -What is Free Float? Free Float, on the other hand, refers to the amount of time that a task can be delayed without affecting the start date of its subsequent tasks. It is calculated as the difference between the earliest possible start date of the next task and the latest possible finish date of the current task.

Detailed explanation-3: -There are two types of float in project management, free float (FF) and total float (TF). Free float is the amount of time that a task can be delayed without impacting the subsequent task. Total float is the amount of time a task or a project can be delayed without impacting the overall project completion time.

Detailed explanation-4: -Total float. The total amount of time a scheduled task can be delayed or extended before affecting a project completion date. Free float. Free float is similar to total float as far as calculations. Project float. Interfering float. Independent float. 28-Sept-2022