Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
It is not necessary to complete all of the activities on the network diagram in order for the project to finish.
A
False
B
True
C
Either A or B
D
None of the above
Explanation: 

Detailed explanation-1: -A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates. An activity is an element of work that has an expected duration, cost, and resource requirements. Critical chain scheduling assumes that resources multitask and maximizes multitasking.

Detailed explanation-2: -Which of the following is true of a finish-to-finish dependency? It is a dependency in which the “from” activity must be finished before the “to” activity can be finished.

Detailed explanation-3: -Fast-tracking is a technique where activities that would have been performed sequentially using the original schedule are performed in parallel.