Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
The client has given you a project to construct a cold storage plant. Everything was going as planned, however, due to some unforeseen incidents, your project is delayed. The client is in a hurry and has threatened you with a large penalty if you are not able to complete the project on time. So, you started working hard to complete the project and avoid the fine. You are working overtime, bringing in more resources from other projects, and renting extra equipment; finally, you complete the project on time. This is an example of:
|
Resource smoothing
|
|
Fast tracking
|
|
Crashing
|
|
Resource leveling
|
Explanation: