Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
When sequencing project activities in the schedule, you should ensure-
|
There always are scheduled dates for specific milestones
|
|
Every activity is connected to at least one predecessor and at least one successor
|
|
Lead or lag time should be used in each schedule
|
|
Necessary sequencing of events may be described by the activity attributes
|
Explanation:
Detailed explanation-1: -Activity Sequencing. Step 2: Activity Sequencing involves the accurate identification of constraints/relationships among activities and establishing the order in which the activities will be accomplished.
Detailed explanation-2: -Project activities are actions undertaken by the project to achieve the set objectives. They are very concrete actions that are practical and well defined.
There is 1 question to complete.