SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

PROJECT SCHEDULING AND TRACKING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
When sequencing project activities in the schedule, you should ensure-
A
There always are scheduled dates for specific milestones
B
Every activity is connected to at least one predecessor and at least one successor
C
Lead or lag time should be used in each schedule
D
Necessary sequencing of events may be described by the activity attributes
Explanation: 

Detailed explanation-1: -Activity Sequencing. Step 2: Activity Sequencing involves the accurate identification of constraints/relationships among activities and establishing the order in which the activities will be accomplished.

Detailed explanation-2: -Project activities are actions undertaken by the project to achieve the set objectives. They are very concrete actions that are practical and well defined.

There is 1 question to complete.