The critical path is established by calculating the following dates:
A
Start-to-start, start-to-finish, finish-to-finish, finish-to-start.
B
Early start, early finish, late start, late finish.
C
Predecessor-to-successor, predecessor-to-predecessor, successor-to-successor.
D
Primary-to-secondary, primary-to-finish, secondary-to-secondary, finish-to-finish.
Explanation: 

Detailed explanation-1: -The critical path method calculates the early dates (Early Start and Early Finish), late dates (Late Start and Late Finish) and total slack. Early Start represents the earliest date an activity can possibly begin, based on all its predecessors and successors.

Detailed explanation-2: -Early Start – The earliest time that an activity can start. Early Finish – The earliest time that an activity can finish. Late Start – The latest time that an activity can start. Late Finish – The latest time that an activity can finish.