Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
The duration of the activity is affected by all of the following EXCEPT:
|
The estimated activity resource requirements.
|
|
The types of resources assigned to the activity.
|
|
The availability of the resources assigned to the activity.
|
|
Using the precedence diagramming method (PDM) for scheduling activities instead of using the critical path method (CPM).
|
Explanation:
Detailed explanation-1: -Which of the following is true related to activities on the critical path? Delays in these activities will delay in the entire project.
Detailed explanation-2: -Critical Path Method (CPM) Scheduling is the most widely used scheduling technique in the Transportation market. This scheduling technique is used to plan and control a project and to calculate the minimum completion time for a project along with the possible start and finish times for the project activities.