The customer on a project tells the project manager they have run out of money to pay for the project. What should the project manager do first?
A
Shift more of the work to later in the schedule to allow time for the customer to get the funds.
B
Close Project or Phase.
C
Stop work.
D
Release part of the project team.
Explanation: 

Detailed explanation-1: -The customer on a project tells the project manager they have run out of money to pay for the project. What should the project manager do FIRST? A. Shift more of the work to later in the schedule to allow time for the customer to get the funds.

Detailed explanation-2: -Project closure is the last phase of a project. It’s when the project manager verifies that the client, stakeholder or customer has accepted the project deliverables. If the project or product is ongoing after the project, then maintenance must be set up.

Detailed explanation-3: -After the project is complete, the project closure statement must be finalized and archived for future use by all concerned parties. To make a formal presentation to senior management, it’s critical that team members be made aware of where the report can be found.

Detailed explanation-4: -Customer satisfaction survey. Monitoring of customer complaints through helpdesk. Monitoring of recurring purchases through CRM. Monitoring of social media engagement. Online sentiment monitoring. 25-Nov-2019