The primary customer of a project has requested an application change during user testing. As project manager, how should you address this issue?
|
Develop a risk mitigation plan.
|
|
Create a formal change request.
|
|
Inform the project sponsor of changes to scope, cost, and schedule.
|
|
Ensure the scope change complies with all relevant contractual provisions.
|
Explanation:
Detailed explanation-1: -When it comes to changes, the project manager’s attention is BEST focused on: Making changes. Tracking and recording changes.
Detailed explanation-2: -A Project management plan is a formal, approved document that defines how the project is executed, monitored, and controlled. It may be a summary or a detailed document and may include baselines, subsidiary management plans, and other planning documents.