Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
You are creating a schedule duration estimate for the activities in the PDR Project. You’re working with your project team and comparing the results of a past similar project to predict the schedule for the current project. What estimating approach are you using?
|
Organizational process assets
|
|
Parametric
|
|
Analogous
|
|
PERT
|
Explanation:
Detailed explanation-1: -The three calculations that must be performed to determine the project duration and the critical path are the forward pass, the backward pass, and the total oat calculations.
Detailed explanation-2: -A successor activity is the schedule activity that follows a predecessor activity, as determined by their logical relationship. The most common type of logical dependency to determine the sequence of project activities is “finish-to-finish” (FF).
Detailed explanation-3: -The answer is D. Inspection includes activities such as measuring, examining, and validating to determine whether work and deliverables meet requirements and product acceptance criteria.