Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The project manager has just received a change request from the customer that does not affect the project schedule and is easy to complete. What should the project manager do first?
A
Make the change happen as soon as possible.
B
Contact the project sponsor for permission.
C
Go to the change control board.
D
Evaluate the impacts on other project constraints.
Explanation: 

Detailed explanation-1: -The project manager has just received a change from the customer that does not affect the project schedule and is easy to complete. What should the project manager do FIRST? The other impacts to the project should be evaluated first. Such impacts include scope, cost, quality, risk, resources, and customer satisfaction.

Detailed explanation-2: -When it comes to changes, the project manager’s attention is BEST focused on: Making changes. Tracking and recording changes.

Detailed explanation-3: -Answer is (D) Work to prevent changes It is important for project managers that the project baseline is not being changed fr…