While important to the control schedule process, which of the following would not be an anticipated output of the control schedule process?
A
Schedule forecasts
B
Change requests
C
Work performance information
D
Schedule compression
Explanation: 

Detailed explanation-1: -Schedule compression refers to a series of techniques used to shorten the duration of a project without compromising the result. Common schedule compression techniques include crashing, fast-tracking and resource reallocation.

Detailed explanation-2: -According to the Project Management Institute (PMI), the process for monitoring schedule progress against the baseline is called control schedule. Project planning, monitoring, and controlling all go together when executing a project and keeping it on track to meet your deadlines.