Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
While important to the control schedule process, which of the following would not be an anticipated output of the control schedule process?
|
Schedule forecasts
|
|
Change requests
|
|
Work performance information
|
|
Schedule compression
|
Explanation:
Detailed explanation-1: -Schedule compression refers to a series of techniques used to shorten the duration of a project without compromising the result. Common schedule compression techniques include crashing, fast-tracking and resource reallocation.
Detailed explanation-2: -According to the Project Management Institute (PMI), the process for monitoring schedule progress against the baseline is called control schedule. Project planning, monitoring, and controlling all go together when executing a project and keeping it on track to meet your deadlines.
There is 1 question to complete.