Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The project manager’s many responsibilities include being or service to the team, integrating new team members as the project progresses, and ensuring that the project meets its objectives within scope, time, budget, and other constraints. Which of the following best describes the project manager’s role as an integrator?
A
Help team members become familiar with the project.
B
Put all the pieces of a project into a cohesive whole.
C
Put all the pieces of a project into a program.
D
Get all team members together into a cohesive whole.
Explanation: 

Detailed explanation-1: -The correct answer is (C) Create a WBS. WBS allows to break a project into manageable units by all team members, each level of the WBS for deepening the details of the tasks to final level: the concrete tasks to perform .

Detailed explanation-2: -#1 Planning everything from execution to delivery. #2 Directing the team to achieve a common goal. #3 Delegating work effectively. #4 Managing the resource of time. #5 Managing the deployment deliverables. More items

There is 1 question to complete.