SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

PROJECT SCHEDULING AND TRACKING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The precedence diagramming method (PDM) is:
A
A technique in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
B
A method that uses a probabilistic approach to scheduling project activities
C
A time-phased graphical representation of the arrow diagramming method (ADM), and shows durations of project activities as well as their dependencies
D
More accurate than the critical path method for scheduling when there are uncertainties about the durations of project activities.
Explanation: 

Detailed explanation-1: -The 4 types of logical relationships in the precedence diagraming method are: Finish-to-Start (FS) dependency, Finish-to-Finish (FF) dependency, Start-to-Start (SS) dependency, and.

Detailed explanation-2: -Finish-to-Start, Start-to-Start, Finish-to-Finish, Start-to-Finish.

There is 1 question to complete.