The precedence diagramming method (PDM) is:
|
A technique in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
|
|
A method that uses a probabilistic approach to scheduling project activities
|
|
A time-phased graphical representation of the arrow diagramming method (ADM), and shows durations of project activities as well as their dependencies
|
|
More accurate than the critical path method for scheduling when there are uncertainties about the durations of project activities.
|
Explanation:
Detailed explanation-1: -The 4 types of logical relationships in the precedence diagraming method are: Finish-to-Start (FS) dependency, Finish-to-Finish (FF) dependency, Start-to-Start (SS) dependency, and.
Detailed explanation-2: -Finish-to-Start, Start-to-Start, Finish-to-Finish, Start-to-Finish.