Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
The WBS, estimates for each work package, and the network diagram arc completed. The next thing for the project manager to do is:
|
Sequence the activities
|
|
. Validate that they have the correct scope
|
|
Create a preliminary schedule and get the team approval.
|
|
Complete risk management.
|
Explanation:
Detailed explanation-1: -A hierarchical listing of what must be done in a project is called: Work breakdown structure (WBS). A method used for establishing a logical framework for identifying the required activities for the project is called: Work breakdown structure.
Detailed explanation-2: -Question: Which of the following should a project manager do to create a WBS? Delegate the WBS creation to project team members Use stakeholder expectations to sequence the activities Obtain approval for each section of the WBS from the project sponsor Collaborate with experienced and knowledgeable individuals.