Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You are constructing a school building and due to some unforeseen incidents, your project is delayed. To bring the project on schedule, you are thinking about running several activities in parallel which were earlier planned to run sequentially. So, you started reviewing activities such as excavation of foundation, building walls, carpentry work, electrical work, and plumbing work, etc. After the review, you decide to run the carpentry, electrical, and plumbing works together. Excavating the foundation for the construction of a wall is an example of which of the following?
A
Mandatory dependency
B
Discretionary dependency
C
External dependency
D
Internal dependency
Explanation: 

Detailed explanation-1: -Many owners require detailed construction schedules to be submitted by contractors as a means of monitoring the work progress. The actual work performed is commonly compared to the schedule to determine if construction is proceeding satisfactorily.

Detailed explanation-2: -Level of Schedules are a Project Master Schedule (Level 1), Project Summary Schedule (Level 2), Control Level Schedule (Level 3), Detailed Network Schedule (Level 4), and Reports Schedule (Level 5).