Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
There are purposes and benefits in the Control Schedule process. Its benefit is-
|
It maintains the schedule baseline
|
|
It minimizes risk
|
|
It reprioritizes remaining work as required
|
|
It describes how the schedule will be managed and controlled
|
Explanation:
Detailed explanation-1: -The Control Schedule process happens on an ongoing basis throughout the execution part of a project. As you are doing the work, you are constantly going back to the schedule to track your progress, make changes and ensure the schedule still reflects reality. As a result, the biggest output of the process is changes.