Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
To help them determine the schedule baseline, the team has drafted a network diagram. “The project manager adds the time estimates for each activity to establish the critical path for the project. They discover the project has three critical paths. Which of the following best describes how this discovery will affect the project?
A
It make it easier to mange
B
lt increases the project risk
C
lt requires more people
D
lt makes it more expensive
Explanation: 

Detailed explanation-1: -(41) Which of the following methods is least likely to be used for explaining project planning guidelines to the team? Hint − A report gives information about what happened and doesn’t talk about planning or give guidelines or directives.

Detailed explanation-2: -The critical path is the sequence of schedule activities determining the duration of the project, and is generally the shortest path through the project. If the project manager changes an activity on the critical path to start at a later date, then the whole project will end at a later date.

There is 1 question to complete.