Tommy is managing a project to build a gelignite plant in Southern California, on a surprising cheap piece of real estate on the side on the San Bernardino Mountains. However, the project has started to slide and a means of reducing the critical path has to be found. Tommy eventually decides to fast track the critical tasks. However, Fast tracking will increase the project ____ ?
A
Risk
B
Scope
C
Cost
D
Time
Explanation: 