You arc a project manager on a $5, 000, 000 software development project. While working with your project team to develop a network diagram, you notice a series of activities that can be worked in parallel but must finish in a specific sequence. What type of activity sequencing method is required for these activities?
A
Precedence diagramming method
B
Arrow diagramming method
C
. Critical path method
D
Operational diagramming method
Explanation: 

Detailed explanation-1: -Key Takeaways. A Gantt chart is a visualization that helps in scheduling, managing, and monitoring specific tasks and resources in a project. It consists of a list of tasks and bars depicting each task’s progress. It’s the most widely used chart in project management.

Detailed explanation-2: -Network diagrams are schematic displays of project schedule activities and the interdependencies between these activities.