____ is a network diagramming technique used to predict total project duration.
A
Gantt chart
B
Critical path analysis
C
Critical task analysis
D
None of the above
Explanation: 

Detailed explanation-1: -The critical path method (CPM) is a technique that’s used by project managers to create a project schedule and estimate the total duration of a project.

Detailed explanation-2: -PERT is a project time management technique. It is used for estimating the project duration when there is uncertainty in the estimation of individual activity duration. It is a network analysis technique.

Detailed explanation-3: -There are two main types of network diagrams in project management: the arrow diagramming method (ADM), also known as “activity network diagram” or “activity on arrow”; and the precedence diagramming method (PDM), also known as “node network” or “activity on node.”

Detailed explanation-4: -Description: Critical path analysis is a project-management technique that lays out all of the activities needed to complete a task, the time it will take to complete each activity and the relationships between the activities.