You are a project manager on a US $5, 000.000 software development project. While working with your project team to develop, 1 network diagram, your data architects suggest that quality could be improved if the data model is .1pproved by senior management before moving on-to other design elements. they support this suggestion with an article from a leading software development iournal. Which of the following best describes this, type of input?
A
Mandatory external dependency
B
Discretionary external dependency
C
External regulatory dependency
D
Heuristic
Explanation: 