SOFTWARE PROJECT MANAGEMENT
PROJECT SCHEDULING AND TRACKING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
You are a project manager on a US $5, 000.000 software development project. While working with your project team to develop, 1 network diagram, your data architects suggest that quality could be improved if the data model is .1pproved by senior management before moving on-to other design elements. they support this suggestion with an article from a leading software development iournal. Which of the following best describes this, type of input?
|
Mandatory external dependency
|
|
Discretionary external dependency
|
|
External regulatory dependency
|
|
Heuristic
|
Explanation: