SOFTWARE PROJECT MANAGEMENT
PROJECT SCHEDULING AND TRACKING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
Early finish minus the early start.
|
|
Zero
|
|
One
|
|
The duration of the project
|
Detailed explanation-1: -A milestone is a task with zero duration. It appears on the Gantt chart as milestone symbol. Milestones are generally used to indicate important dates on the project plan, often key events or goals. For example, you might use milestones to mark desired completion dates, or project review meetings.
Detailed explanation-2: -Milestones typically have zero duration; however, some milestones may need a duration. For example, your project has an approval milestone at the end of a phase, and you know that the approval process will take a week.
Detailed explanation-3: -A milestone is an important event in a project. It represents a moment in time wherein the team members have achieved an important event for the project. Thus, it should be assigned zero duration.