Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You are assigned as the project manager in the middle of the project. The project is within the baselines, but the customer is not happy with the performance of the project. What is the first thing you should do?
A
Discuss it with the project team.
B
Recalculate baselines.
C
Renegotiate the contract.
D
Meet with the customer.
Explanation: 

Detailed explanation-1: -According to the PMBOK: “Managing project scope is primarily concerned with defining and controlling what is and is not included in the project.”

Detailed explanation-2: -A baseline in project management is a clearly defined starting point for your project plan. It is a fixed reference point to measure and compare your project’s progress against. This allows you to assess the performance of your project over time.

Detailed explanation-3: -Planning The plan established during this process helps project managers oversee scope, cost, timelines, risk, quality issues, and communications. It is during this phase that project managers will outline key deliverables and milestones and identify the tasks that must be completed to complete each.