SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

PROJECT SCHEDULING AND TRACKING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You are working collaboratively with the team to plan a project. You have obtained estimates from team members on the activities for which they each will be responsible. You are currently reaching agreement on the calendar dates for each activity. Which of the following processes are you working on?
A
Sequence Activities
B
Develop Schedule
C
Defu1e Scope
D
Develop Project Charter
Explanation: 

Detailed explanation-1: -2. Which team member did you assign to own the task, “supervise vendor installation of fulfillment equipment”? Correct: The Fulfillment Director ensures equipment is functional, so they should supervise the installation.

Detailed explanation-2: -To help them determine the schedule baseline, the team has drafted a network diagram. The project manager adds the time estimates for each activity to establish the critical path for the project.

There is 1 question to complete.