Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You are managing an interior decorating project. The walls are scheduled to be painted immediately after the primer is applied. You have allowed 36 hours between the primer activity and the painting activity to ensure that the primer has cured. This is an example of which one of the following?
A
Lead
B
Soft logic
C
Finish-to-start relationship
D
Lag
Explanation: 

Detailed explanation-1: -The walls are scheduled to be painted immediately after the primer. You have allowed 36 hours between the primer activity and the painting activity to ensure that the primer has cured. This is an example of which one of the following? (The time between the activities is lag time.

Detailed explanation-2: -If the project manager changes an activity on the critical path to start at a later date, then the whole project will end at a later date. To use the enumeration method of determining the critical path, we list or enumerate all of the paths through the network.

Detailed explanation-3: -The project charter often mentions planned project start and end dates, which serve as the starting points for a more detailed schedule. A schedule management plan includes information which describes the format and frequency of schedule reports required for the project.

Detailed explanation-4: -Define the scope of change. Evaluate the impact of potential change. Adjust project plans. Communicate and implement the approved change request. Use project management tools. Understand how to identify risk. Develop a change management plan. 03-Feb-2023