SOFTWARE PROJECT MANAGEMENT
PROJECT SCHEDULING AND TRACKING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Decomposition is a technique used for both WBS development and activity definition. However, in Define Activities, decomposition-
|
The final output is described in terms of work packages in the WBS.
|
|
The final output is described as deliverables or tangible items.
|
|
The final output is described as activities.
|
|
Is used the same way in scope definition and activity definition.
|
Explanation: